The project

Gifford StreetA re-development of the Gifford Street area of Lewisham to provide necessary facilities for the local area, including a new-build multi-residential development consisting of 40 apartments and 8 studios.

 

The Challenge

To provide centralized on-site electricity and hot water generation for the apartment building in line with The London Plan.

Summary of site demand

Annual electricity demand…………………………………………… 109,516 kWh

Electricity price (without CCL)………………………………………….. 9.0 p/kWh

Gas consumption………………………………………………………. 227,361 kWh

Gas price (without CCL)…………………………………………………… 3.0 p/kWh

The solution

Supplied and installed one 15kWe/30kWth

LoadTracker CHP unit to provide 86% of site heating and hot water demand.

Featurescase-study-gun-wharf-image6

  • LoadTracker automatically modulates electrical output, which minimizes unnecessary grid electricity consumption.
  • Long service intervals (8,000 hours or 2 years).
  • Provides on-site energy generation through the development of a new CHP distribution network.

Benefits

  • Consumption & Production
  • Carbon Footprint Savings
  • Cost Savings

Consumption & Production

Consumption & Production

Carbon footprint savings

25 tonnes of CO2 emissions could be reduced annually by installing a CHP system relative to a conventional mains supply/ gas boiler system.

This is an equivalent 24% reduction of CO2 emissions.

Carbon footprint savings

Carbon footprint savings

Cost Savings

The use of LoadTracker CHP would result in annual savings of £4,101 relative to a conventional mains electricity supply/ boiler system.

This is equivalent to saving 25% on energy bills.